When can slab formwork be stripped?
The time to strip a slab is set by the strength of the concrete, not by the calendar. Here is what it depends on, who decides, and why the props often stay under a slab longer than the formwork.
In short
- A slab can be stripped once the concrete reaches the strength required by the structural design or specified by the designer – not after a fixed number of days.
- The strength class of concrete refers to a test after 28 days of curing in standard conditions. On site, especially in cold weather, concrete gains strength more slowly.
- Below about +5°C concrete hardens much more slowly, and below freezing it practically stops.
- Side formwork comes off first; the soffit formwork and props only once the required strength is reached, gradually and in a set order.
- The site manager decides on stripping, based on the design and the state of the concrete.
What the stripping time depends on
Formwork and props carry the weight of fresh concrete, reinforcement and construction loads until the slab can carry them itself. When that happens depends mainly on:
- the concrete class and the type of cement – high early strength cements (marked R) harden faster than cements with a large share of additions,
- the temperature and humidity while the concrete cures,
- the span and thickness of the slab,
- the loads the slab takes right after stripping – the walls of the next storey, pallets of materials or the fresh concrete of the slab above,
- curing, i.e. keeping the concrete wet and shielding it from sun, wind and frost.
Why there is no single number of days
Guides often quote fixed periods, but these are rough values for typical conditions. The same concrete mix hardens differently in July and in November.
The strength class of concrete (e.g. C20/25 or C25/30) is based on tests of samples cured for 28 days in laboratory conditions. That is why about four weeks is the usual reference point for planning the works and the formwork hire. What is binding, however, is the structural design or the designer’s instructions and, when in doubt, a test of the concrete strength – for example samples kept in the same conditions as the slab, or a non-destructive test.
Weather: cold extends the time, heat calls for curing
Below about +5°C cement hydration slows down considerably, and below freezing it practically stops. Young concrete that freezes can permanently lose strength. In autumn and winter the stripping time must be planned with a margin, or cold-weather concreting methods set by the designer or concrete technologist must be used.
In hot weather concrete loses water quickly. Without wetting and covering it can crack and fall short of its design properties – so heat is no reason to strip a slab early.
Side formwork, soffit formwork and props – what comes off first
Side formwork, such as the slab edges or the sides of beams, does not carry the weight of the slab, so it comes off earlier – once the concrete is hard enough not to damage the edges.
The soffit formwork and the props are removed only after the required strength is reached. This is done gradually and in a set order, so the slab does not suddenly take its full load or work in a way the design did not foresee. Some formwork systems have drop heads that let the beams and plywood come off earlier while the props stay – whether and when that is allowed is the site manager’s call.
When the next slab is cast, the weight of the fresh concrete passes through the props to the slab below, so that slab may need propping too. For beam-and-block slabs, the number, spacing and duration of the temporary props are set by the slab system manufacturer and the designer.
Who decides on stripping
The site manager organises and runs the works in line with the design and the regulations (Article 22 of the Construction Law). It is the site manager who – based on the structural design, the designer’s or slab manufacturer’s instructions and the state of the concrete – decides when the formwork and props can come out. A contractor should not strip a slab on their own just because an agreed number of days has passed.
Where a build runs without a site manager, for example a house of up to 70 m² footprint built on a notification, the investor takes over responsibility for running the works – and with it the decision on stripping.
What happens if a slab is stripped too early
A slab relieved of its supports too early can deflect excessively and crack, and part of that deflection may stay for good. In extreme cases the structure can fail. Repairing such defects is difficult and costly, so a few extra days of propping are cheaper than the risk of rushing.
Questions and answers
Can the props come out from under a slab after 7 days?
There is no such general rule. After a week concrete usually has not reached its design strength yet, especially in cold weather. Whether the props can come out is for the site manager to decide, based on the design and the state of the concrete – often some props stay longer.
Is a slab stripped at the same time in winter as in summer?
No. At low temperatures concrete hardens more slowly, and below zero the process practically stops. In winter the stripping time is longer and should follow the actual state of the concrete, not a number of days.
Can a slab be loaded right after stripping?
With care. A freshly stripped slab usually does not have its full strength yet, so heavy materials should not be stacked on it, nor the next storey cast, without agreement from the site manager.
Legal basis and standards
- Polish Construction Law – Article 22 (duties of the site manager)
- PN-EN 206 – Concrete. Specification, performance, production and conformity (strength classes)
- PN-EN 13670 – Execution of concrete structures (falsework and formwork)
This article is general information and does not replace the design or the decisions of the people holding technical roles on a specific build.
Related service
More guides
- Site manager versus supervision inspector – who do you need to build a house?What the site manager and the investor supervision inspector are responsible for, when each is mandatory for building a house, and why one person cannot hold both roles.
- The site log (dziennik budowy) – who keeps it and what goes in it?When a site log is required, how to obtain one, who keeps it and who may write in it, what goes in it and how the paper version differs from the electronic one (EDB).