The site log (dziennik budowy) – who keeps it and what goes in it?

The site log (dziennik budowy) is an official document recording the course of the works. Here is when it is required, who keeps it, who may make entries and how the paper version differs from the electronic one (EDB).

In short

  • A site log is kept for works that require a site manager (Article 45 of the Construction Law).
  • The investor applies for the log; the architectural and building authority issues it within 3 working days (Article 47g).
  • The site manager is responsible for keeping the log (Article 47d).
  • Entries are made by the participants in the building process, the surveyor working on site and staff of inspection authorities (Article 47e).
  • The log is kept on paper or electronically in the EDB system; paper logs are issued until 31 December 2031 (Article 47v).

What the site log is

The site log is an official document for recording the course of the construction works and the events and circumstances during them that matter for judging whether the works were carried out correctly (Article 47a of the Construction Law). They are recorded as entries.

Since 2023 the rules on the site log have been in Chapter 5a of the Construction Law (Articles 47a–47v), with the details set out in the regulation on the site log and the Electronic Site Log (EDB) system.

When a site log is required

A site log is kept for construction works that require a site manager (Article 45). That includes building a single-family house under a building permit or on a notification with a building design. A separate log is kept for each building that requires a permit or a notification (Article 47b).

It is not kept for works that do not need a site manager – for example a house of up to 70 m² footprint built on a notification for the investor’s own housing needs.

How to obtain a site log

The investor applies to the architectural and building authority – for a house this is usually the district office (starostwo) or the city office of a city with district rights (Article 47g). The log is issued within 3 working days, but not before the building permit becomes final or the works may start under the notification.

A paper log is issued by the authority stamping a log submitted by the investor. An electronic log is set up by applying in the EDB system, and once issued it gets an individual number (Article 47h). The investor also makes sure copies of the building qualifications of the site manager, works managers and supervision inspector are attached to the log – unless they appear in the central register of qualified persons (Article 47f).

Before the works start, the site manager confirms in the log that they received the building design from the investor (Article 45a(1)(2)).

Who keeps the log and who may make entries

The site manager is responsible for keeping the site log in line with the law (Article 47d). Entries may be made by (Article 47e):

  • the participants in the building process – the investor, the investor supervision inspector, the designer, the site manager and works managers,
  • a licensed surveyor carrying out survey work on site,
  • authorised staff of the building control and other inspection authorities – during an inspection on site.

What goes into the site log

The law has no closed list of entries – anything that matters for judging whether the works were done correctly goes in. In practice typical entries cover:

  • taking over the site and confirming receipt of the design,
  • the setting out of the building by the surveyor,
  • reporting and accepting work that will be covered up or concealed – such as reinforcement before concreting,
  • the key stages, such as casting the foundations and slabs,
  • instructions from the supervision inspector and the designer, and the responses to them,
  • stopping the works, changes in the people holding technical functions and other significant events,
  • the site manager reporting the building for acceptance.

Paper or electronic log (EDB)

The site log is kept either on paper or electronically (Article 47c). The electronic version is kept in the Electronic Site Log (EDB) system, in operation since 2023. Everyone who makes entries needs an account in the system, and the investor grants access to the log (Articles 47n and 47o).

A paper log can be continued electronically, but an electronic log cannot go back to paper (Article 47k). Paper logs are issued until 31 December 2031 (Article 47v).

Closing the log and completing the build

When the works are finished, the site manager closes the log with an entry; in EDB the log then gets the status “closed” (Article 47l). Once a notice of completion is accepted without objection, or an occupancy permit is issued, the building control authority gives it the status “handed over for use”.

With the notice of completion or the application for an occupancy permit, the investor generally attaches the original paper log or gives the number of the electronic one (Article 57(1)(1)). Single-family houses are exempt from this requirement (Article 57(1b)). It is still worth keeping the log with the rest of the construction documentation.

Questions and answers

Is a site log needed for a house built on a notification?

Yes, if the works require a site manager – which is the case for a single-family house built on a notification with a building design. The exception is a house of up to 70 m² footprint for the investor’s own housing needs, where no site manager is appointed and no log is kept.

Can you switch from a paper log to an electronic one during the build?

Yes. The investor applies for an electronic log and the site manager closes the paper log with an entry. It does not work the other way – an electronic log stays in EDB until the end.

Who may make an entry in the site log?

The participants in the building process (investor, investor supervision inspector, designer, site manager and works managers), the surveyor working on site, and staff of building control and other inspection authorities during an inspection.

Legal basis and standards

  • Polish Construction Law – Articles 45 and 45a
  • Polish Construction Law – Chapter 5a, Articles 47a–47v (site log, EDB system)
  • Polish Construction Law – Article 57 (documents for completing the build)
  • Regulation on the site log and the Electronic Site Log system (Journal of Laws 2023 item 45)

This article is general information and does not replace the design or the decisions of the people holding technical roles on a specific build.