Site manager versus supervision inspector – who do you need to build a house?
A site manager is, as a rule, mandatory for building a house in Poland; an investor supervision inspector is usually optional. Here is what each is responsible for and when it is worth having both.
In short
- The site manager runs the works and is responsible for carrying them out in line with the design and the regulations (Article 22 of the Construction Law).
- The investor supervision inspector represents the investor and checks the quality of the works and the contractor’s performance (Article 25).
- A site manager must be appointed, among other cases, for a house built under a building permit or a notification with a design (Article 42(1)(2)).
- A supervision inspector is mandatory when the building permit or the regulations for that type of building require one – for a typical single-family house the investor appoints one by choice.
- The roles of site manager and supervision inspector may not be combined on the same build (Article 24(1)).
Site manager – what they are responsible for
Running a build is an independent technical function in construction (Article 12 of the Construction Law). It may be performed by a person with building qualifications in the relevant speciality who is a member of the professional chamber. The site manager’s core duties (Article 22) include:
- taking over the site from the investor against a record and securing it,
- keeping the construction documentation, including the site log,
- organising and running the build in line with the design, technical building regulations and health and safety rules,
- stopping the works when a hazard is found and promptly notifying the relevant authority,
- reporting work that will be covered up or concealed to the investor for checking or acceptance,
- reporting the finished building for acceptance with an entry in the site log.
At the end of the build the site manager signs a statement that the building was built in line with the design and the regulations; the investor attaches it to the notice of completion or the application for an occupancy permit (Article 57(1)(2)). The site manager may be hired by the investor or by the contractor – when a house is built by separate trades, the investor usually hires one directly.
Investor supervision inspector – the investor’s representative
The investor supervision inspector acts on behalf of the investor. Their core duties (Article 25) are:
- checking that the build complies with the design, the regulations and good engineering practice,
- checking the quality of the works and of the building products used,
- checking and accepting work that will be covered up or concealed, and taking part in tests, technical inspections and the acceptance of the finished building,
- confirming work actually done and defects remedied and, at the investor’s request, checking the build’s accounts.
The inspector may give the site manager instructions confirmed by an entry in the site log, demand that defective work be redone and, where continuing could cause a hazard or a serious departure from the design, demand that the works stop (Article 26).
When a site manager is mandatory
The investor must appoint a site manager in the cases listed in Article 42(1)(2) of the Construction Law. They include works carried out under a building permit and building a single-family house on a notification with a building design. The authority may waive this by decision, but only because the works are of minor complexity or for other important reasons (Article 42(3)).
The exception is a house of up to 70 m² footprint built on a notification to meet the investor’s own housing needs (Article 29(1)(1a)). No site manager is required there – the investor takes over responsibility for running the build and signs a statement to that effect.
When a supervision inspector is mandatory, and when it is worth having one
As a rule the investor may, but does not have to, appoint an investor supervision inspector (Article 18(2)). It becomes mandatory when the building permit requires it or when the building belongs to the types listed in the regulation issued under Article 19(2) (Article 42(1)(3)). For a typical single-family house, appointing an inspector is usually the investor’s choice.
An inspector is especially useful when the site manager is employed by the contractor and the investor wants someone on site who looks at the works purely from the investor’s side – and when the investor cannot visit often or has no technical background.
Why the two roles cannot be combined
Article 24(1) of the Construction Law states plainly that combining the roles of site manager and investor supervision inspector is not permitted. The site manager is responsible for carrying out the works and the inspector checks them – one person cannot check their own work. The same engineer can, however, be the site manager on one build and the supervision inspector on another.
Questions and answers
Can the investor be the site manager of their own house?
Yes, if they hold building qualifications in the relevant speciality and are a member of the professional chamber. Without qualifications they cannot – except for a house of up to 70 m² built on a notification, where the investor takes over responsibility for running the build.
Does the site manager have to be on site every day?
The law does not say how often the site manager must visit. They must, however, be there often enough to actually run the works – in practice always at the key stages and when work that will be covered up is accepted.
Who hires the investor supervision inspector?
The investor. The inspector acts on behalf of the investor, independently of the contractor. A site manager, on the other hand, may be hired by either the investor or the contractor.
Legal basis and standards
- Polish Construction Law – Article 12 (independent technical functions)
- Polish Construction Law – Articles 18, 19 and 42 (duties of the investor)
- Polish Construction Law – Article 22 (duties of the site manager)
- Polish Construction Law – Article 24 (ban on combining roles)
- Polish Construction Law – Articles 25 and 26 (duties and rights of the supervision inspector)
- Polish Construction Law – Article 57 (documents for completing the build)
This article is general information and does not replace the design or the decisions of the people holding technical roles on a specific build.
Related service
More guides
- When can slab formwork be stripped?What the stripping time of a slab depends on, why there is no single number of days, how the weather affects it and who decides when the formwork and props come out.
- The site log (dziennik budowy) – who keeps it and what goes in it?When a site log is required, how to obtain one, who keeps it and who may write in it, what goes in it and how the paper version differs from the electronic one (EDB).